 Project Overview
Welcome to the Questar Gas
Feeder Line 4,5 and 11 Capacity Enhancement Project Website.


Between November 2007 and December 2008, Questar Gas will replace three contiguous sections of its system in the Salt Lake Valley known as Feeder Line 4, 5 and 11. (Feeder lines are larger, steel pipelines that supply smaller main and individual service lines which connect to meters at homes and businesses.)

This work is necessary to keep pace with increased demand for natural gas due to customer growth. It will also enhance our ability to continue providing safe, reliable natural gas service by making our system easier to monitor and maintain.

Most of the 16 miles of pipe slated for replacement are located under 3300 South and 3500 South streets between 2700 East and 6680 West. At 6680 West, the remainder of the pipe runs diagonally in a northwesterly direction to a crossover valve at the corner of 9180 West and 2400 South. (See link to map at left.)

This project will involve some nighttime and weekend work and lane restrictions. Watch this site for the latest traffic information. To avoid congestion in construction zones, motorists are advised to use alternate routes and to allow plenty of travel time to get where they're going.

This website provides general information about the project as well as current information on construction activity and related impacts on local traffic.

For additional information, comments, or to receive weekly updates by email, click here.

Project hotline: (801) 324-5548

Quick Links
UTA Route Detours

UDOT 3300 South Project
UDOT 3500 South Project
Weekly Updates

arrow June 20, 2008 UPDATE

Note: Due to the July 4 holiday, next week will be a short work week. Crews will be off from Thursday, July 4, through Sunday, July 6. Construction activity will resume on Monday, July 7. Due to the holiday, there will be no weekly update issued July 5. The updates will resume on Friday, July 11.

Hunter Park Village – Restoration of the right-of-way has been delayed due to a miscommunication between the city and the contractor that resulted in more...

3300 South – Major construction continues between State Street and 500 West, including the bores under TRAX and I-15. Watch for median closures and lane restrictions EB and WB in more ...

3300/3500 South: Cleanup, repaving and major construction continues between 1000 West and Redwood Road. Consequently, median closures and  more ...

3500 South: Mainline construction continues between Bangerter Highway and 4800 West. Expect median closures and intermittent lanes restrictions EB and WB.