spacer
Salt Lake City System Improvement Projects
spacer
 Construction Updates

arrow July 16, 2014 -- On 900 East, southbound traffic is limited to one lane between 320 South and 360 South. Equipment and pipe are still stationed at the corner of 1000 East and 300 South and cordoned off with construction barriers. On 500 South between 920 East and 960 East, crews are installing Geofoam over the 16-inch-diameter steel pipe where it crosses the fault line. Traffic lanes are open on either side of the excavation. 500 South will be repaved next week. Individual services are all tied into the new 2-inch plastic mains. Next week, crews will be digging and tying in the new steel pipe at 1000 East and 800 South and at 1000 East and 300 South in preparation to “pig” and test the new pipe.

On Main Street, the northbound lane between 300 South and 100 South is still closed to traffic. On 200 South, eastbound traffic is limited to one lane entering the intersection at Main Street to provide room for the bore pit.

arrow July 8, 2014 -- This week on 900 East between 300 South and 400 South, crews will be reconnecting individual service lines to the new eight-inch-diameter plastic main line. They will also be tying in the dead-end main on Iowa Street into the new two-inch-diameter plastic main on 300 South and installing Geofoam over the sixteen-inch-diameter steel main line on 500 South where it crosses a fault line.

On Main Street, NB traffic between 100 South and South Temple will be reopened tomorrow. The NB lane on Main Street between 300 South and 100 South is closed. Sidewalks remain open and there is complete access to TRAX and all businesses. New pipe is installed between 100 South and 200 South. The last two businesses will be reconnected and the line gassed by this weekend. Traffic NB on this block is scheduled to reopen by July 24. Meanwhile, in the block between 300 South and 200 South, crews will be potholing, boring and installing new eight-inch-diameter plastic main. This work is scheduled to be completed by Aug. 8.

arrowJune 25, 2014 -- On 300 South, crews will finish installing new 16-inch-diameter steel pipe between 900 East and 1000 east by the end of this week. They will also begin installing two-inch plastic main on the north side of 300 South and tying in individual services. Once the service lines on 300 South are re-connected, crews will move to 900 East and begin installing new eight-inch plastic main on the west side of the street between 300 South and 400 South.

On Main Street, crews have completed the bore under 100 South and tied in the new eight-inch plastic main on the north side of the intersection. Early next week, once the concrete patch has cured, the northbound lane of Main Street between 100 South and South Temple will be reopened to traffic. Crews are completing installation of new eight-inch plastic main between 100 South and 200 South this week and will begin replacing individual service lines to businesses over the next couple of weeks. Northbound traffic on Main Street between 100 South and 200 South will remain closed until this work is finished. Meanwhile, early next week, northbound traffic between 200 South and 300 South will be closed has crews begin potholing in preparation to install new eight-inch plastic main in that section.

arrow June 16, 2014 -- Work will begin to replace the existing pipe on the east side of Main Street between 100 South and 300 South. Crews will be working from 7 a.m. to 10 p.m. Monday through Saturday. Northbound traffic on Main Street will be closed at various times between 300 South and 100 South while work is underway. Sidewalks will remain open, and the work will not affect TRAX schedules. Construction on this section of Main Street is expected to be finished by Aug. 8, 2014.

arrowJune 6, 2014 -- Crews have completed the bore on 900 East under 400 South and the TRAX line and have installed new 16-inch-diameter steel pipe up to 300 South. Next week, crews will begin installing steel pipe east on 300 South from 900 East to 1000 East. They will also be paving over the trench on 900 East between 300 South and 500 South and adding a little more asphalt on 500 South between 900 East and 1000 East. All services on 1000 East have been connected to the new plastic main line

arrowMay 21, 2014 -- Crews have finished installing new the 16-inch-diameter steel main on 500 South from 1000 East to 900 East and will now begin working north on 900 East. They should reach 400 South by the end of the week. Starting the week of May 27, in preparation for the bore under 400 South and the TRAX line on 900 East, crews will be potholing in the intersection to locate existing buried utilities. They'll also be working on the north and south side of 400 South and then begin boring under the intersection of 900 east and 400 South. The NB lanes of 900 East from 500 South to 300 South are closed and all traffic diverted to the west side of the street and restricted to one lane NB and SB for the next few weeks. 1000 East between 500 South and 800 south will be re-asphalted by the end of this week. Also this week, all individual services on 1000 East from 500 South to 600 South will be connected to the new main.

arrowMay 12, 2014 -- This week crews will begin preparations for the 16-inch bore on 900 East. To provide room for workers and equipment the north bound lanes of 900 East from 500 South to 300 South will be closed and all traffic diverted to the west side of the street and restricted to one lane NB and SB for the next few weeks. Crews will also be trenching to install the new 16-inch steel pipe on 500 South from 1000 East to 900 East. This work will include boring under a buried canal just east of 900 East. Individual services will be tied into the new 2-inch-diameter plastic main on the west side of 1000 East between 600 and 500 South. Next week (May 19) the road cuts on 1000 East between 500 South and 800 South will be repaved.

arrowMay 1, 2014 -- On 1000 East, crews have installed new 16-inch-diameter steel pipe under the 700 South intersection and down to 800 South. They have also installed new two-inch plastic pipe between 500 South and 800 South and are close to connecting all individual service lines to it. Crews are now open trenching to install new 16-inch steel pipe between 700 South and 600 South and will begin trenching between 500 South and 600 South on Monday, May 6. This week they will install new two-inch plastic on 500 South from 900 East to 1000 East.

arrow April 21, 2014 -- Crews have installed new 2-inch-diameter plastic main on 800 South between McClelland St. (1050 East) and 1000 East and on the east side of 1000 East from 800 South to 700 South. All service lines in this section, as well as the one-way main running east on Lowell Ave. (750 South), have been tied to the new pipe. In addition, crews completed boring and installing a 16-inch-diameter steel main line under the intersection of 600 South and 1000 East. This week, crews will be boring and installing 16-inch steel pipe at the 1000 East and 700 South intersection. They will also install new 2-inch-diameter plastic main on the west side of 1000 East from 700 South to 600 South.