spacer
Feeder Line 6
spacer
Project Schedule


2015 Feeder Line 6 Replacement Project Schedule* -- 1/19/15 to 9/7/15

11400 South to11604 South on 1700 East: Completed 2/26/15

Dimple Dell Park (ROW restoration): 4/27/15 -- 5/22/15

11732 South to Hidden Valley Club Drive on 1700 East: Completed 3/20/15

12400 South to Ellerbeck Ln. (Hillcrest St.): 3/23/15 -- 5/1/15

Dimple Dell to Sego Lilly (behind Smith's): 4/13/15 –- 5/8/15

12400 South -- Hillcrest to Cypress Point Mon: 5/13/15 -- 6/12/15

1700 East to Highland Dr. along Ellerbeck Ln.: 4/20/15 -- 5/29/15

1700 East to Cypress Point: 5/13/15 -- 6/26/15

Ellerbeck Ln. to 13130 South Highland Dr.: 5/25/15 -- 7/2/15

Cypress Point: 6/15/15 -- 7/17/15

Inspect, clean and pressure test new pipe: 7/27/15 -- 8/28/15